Two offshore wind farms off Norfolk can move towards construction at sea after RWE and KKR completed their financing and ownership deals. The developers said on 11 November 2026 that they had reached financial close on Vanguard West and Vanguard East, which together represent about £12 billion of investment in turbines and transmission infrastructure. KKR acquired half of each project, forming a joint venture with Germany’s RWE, which will lead delivery. Project announcement
Key facts
- The developers plan 1.4 GW of generating capacity at each site, for a combined 2.8 GW.
- The financing includes a £1 billion commitment from the UK’s National Wealth Fund.
- In January, both projects secured contracts with a strike price of £91.20 per megawatt hour in 2024 prices.
- The developers expect offshore construction to begin in early 2027 and both projects to be fully commissioned in 2030.
What the investors closed
The January electricity auction awarded revenue support to the wind farms. The November announcement records a different milestone: the developers have secured the equity and project financing to proceed, and the proposed ownership transaction has closed. Both partners are committing equity. RWE says the US investment firm is investing through capital accounts advised by KKR, and that the partners will develop, build and operate the farms together.
The £12 billion describes investment in the two projects, including the infrastructure that will carry their electricity to the grid. The developers separately describe financing facilities of £11.1 billion in cash and £1.7 billion in ancillary facilities from 35 banks. Those are different measures: the facilities describe financing available to the projects, while the investment figure describes what is being built. The UK government confirmed the National Wealth Fund’s £1 billion commitment, which forms part of the financing. RWE also identifies credit cover from Germany’s Euler Hermes and Denmark’s EIFO.
How the power contracts fit in
The Department for Energy Security and Net Zero’s auction results list the same £91.20 strike price, in 2024 prices, for the awarded units of Vanguard East and West. The figure is expressed per megawatt hour of electricity. It is the benchmark used by the support contracts for generation, a different measure from the capital invested in building the farms. The developers say the contracts are indexed for inflation and run for 20 years. The published strike price therefore uses a common price base even though the contracts extend well beyond the construction period.
The farms are planned for waters between 50 and 80 kilometres off the Norfolk coast. Their combined 2.8 GW describes installed generating capacity. RWE estimates their production once operational could supply electricity equivalent to the consumption of about three million UK homes. The government estimates the projects will support more than 2,400 jobs across construction and operation, which covers two stages of work over the life of the development.
Onshore cable and substation work is already well advanced, the developers say. The next physical milestone is at sea: they plan to install the first Vanguard West foundation in the first half of 2027, with Vanguard East to follow. Full commissioning of both farms is expected in 2030.